Consulting Core Services
On-Site Training

GCA can orient the course to any  number of topics but typical ones have included:

  • Basics of the Federal Acquisition Regulation
  • FAR Cost Principles
  • Cost Accounting Standards
  • Working with DCAA
Contact Us

Don't hesitate to contact us if you have any questions, comments, suggestions, or problems with registration.

Phone: 1-925-362-0712

Fax: 925-362-0806

Email GCA

Subscriber Login

Path: Consulting Services arrow Report & Digest arrow GCA Digest Articles arrow GCA Digest 2003 arrow Considerations on ID/IQ Contracts, Claims and Protests - Bidder Beware: IDIQ Contract Risks

Considerations on ID/IQ Contracts, Claims and Protests - Bidder Beware: IDIQ Contract Risks

(Editor’s Note. The following is a guest article by Tim Power of the Law Offices of Tim Power (925-975-0330). We asked him to provide some practical insights and discuss recent developments he encounters in the bidding and awarding of contracts. We have worked with Tim on numerous claims and terminations for clients and have been quite successful in recovering entitled funds.)

Indefinite Delivery Indefinite Quantify contracts provide the government flexibility for requirements that cannot accurately be anticipated. An IDIQ Request for Proposal typically provides estimated quantities as well as a guaranteed minimum ordering quantity. The RFP may require the contractor to maintain the ability to meet these estimated quantities but the government is only required to order whatever minimum is established by the RFP. When pricing such contracts, the contractor needs to be aware that they bear the risk that only the small minimum amount may be ordered. When the minimum is not ordered, the contractor can only recover the profit it would have made if the minimum was ordered, not the difference between what was ordered and the minimum. Estimated quantities are just that and are often developed with an eye toward soliciting the best possible pricing and responsiveness from the contractor. (Editor’s Note. If you are a subcontractor and in a strong negotiating position you may be able to negotiate more favorable terms with your client. For example, you might use a schedule of unit prices where unit prices are higher if overall quantities are lower while offering lower unit prices where overall quantities ordered are higher. Just because the prime contract may be limited to ID/IQ restrictions does not mean all subcontracts need be.)

Two cases decided by the Court of Appeals for the Federal Circuit point out risks contractors face when bidding on IDIQ contracts and they also indicate important distinctions between IDIQ and requirements contracts. In Travel Centre v. Barram, CAFC Nos. 00-1054 and 00-1126 the General Services Administration solicited bids for a base period and four option years for travel management services. The RFP stated the terms would be an IDIQ contract with a "guaranteed revenue minimum of $100." Bidders were told that several agencies would be ordering though the GSA contract and to base their offers on expected revenue commissions of $2,500,000. The GSA learned before offers were submitted that half the agencies would not be ordering through the GSA but did not divulge the expected reduction in orders. Travel Centre was awarded the contract and received only $500,000 in ordered services over nine months before the contract was terminated. It claimed the GSA had breached the contract by failing to disclose the estimated quantities were overstated and sought recovery in lost business damages. The Court ruled against Travel Centre where it stated unlike a requirements contract that mandates the contracting government entity fills its actual needs for supplies and services from the contract awardee, an IDIQ contract provides only that the government orders only a stated minimum quantity of supplies and services which was $100. The fact the estimated quantities were incorrect made no difference because Travel Centre had no right to rely upon them. The lesson of the case is that contractors have no right to rely on the estimates given in the solicitation and that bidding on IDIQ contracts is often a gamble. Even though a lower court ruled that Travel Centre was improperly induced to base its proposal on quantities the GSA knew were overstated and hence breached its contract, the higher court rejected this position stating the government is free to include estimates of work in a solicitation that it knows are wrong. A few savvy questions asked in the pre-bid phase of the solicitation can help decide if it is worth pursuing or if there is too great a gamble. For example, How were the estimates developed? When were the estimates developed and has anything changed? What are the estimates for option years?

In Verilease Technology Group Inc. v. United States CACF No. 01-5114 the contract called for a base year plus four one year option years to provide maintenance to identified computers for a maximum of $50,000,000 and a minimum of $100,000 for the base period only. After award the government replaced several of the identified computers, canceling some orders placed and stopping the placement of new orders. The contract was terminated in the second option period where orders were $3 million in the base period and total orders were $10 million. Because there was only a minimum amount for the base period and none for the option years Verilease argued its contract was a requirements contract not IDIQ where a minimum amount is mandatory and if it prevailed the government would have been required to order all its requirements from it rather than just the minimum amount. The Court ruled against Verilease saying option periods are not the same as a new contract but that there is only one contract for the base period and option years so the $100,000 minimum for the base period covers the entire contract period. Once this minimum is met, there is no obligation of the government to order anything in the option years.

US v. Delta Construction Intl, CAFC No. 01-1253 addresses how much the government has to pay if the minimum guaranteed amount is not met. In the contract to replace rotten lumber in various areas of a military base, the base period plus several option years provided for a minimum of $200,000 of guaranteed work. After the first option period the contract was not renewed and Delta filed a claim of $125,000 for the difference between the value of orders placed and the $200,000 minimum guarantee. Though the Board sided with Delta ruling the contractor was entitled to the difference between the value of orders place and the minimum the higher Court rejected the Board’s position asserting such a position put the contractor in a better position than if the government had ordered the minimum. The Court stated the Board’s position would have provided the contractor with an additional $113,000 without any reduction to reflect Delta’s additional costs of performing the work. Thus when the government does not order the minimum guaranteed amount the contractor is entitled to recover the difference between what was ordered and the minimum less the costs associated with performing the work that should have been ordered to meet the minimum. Thus contractors need to track the costs of performing the work. An attempt should be made to identify the period of greatest profitability to use to calculate the damage. For example, use of a period where there is a shortage of orders might result in lower efficiency and low profit where in a period of high level of orders, work is more efficient and so is profit.

{TAG_FORM_TITLE}

To discuss your needs, contact Bill Lennett, Principal, at 1-925-362-0712 or email him at This e-mail address is being protected from spam bots, you need JavaScript enabled to view it .

*
 
*
 
*
 
 
*
 
 
 

 
GCA Subscription
REPORT FEATURES
  • New Developments-Rule Changes, New Guidelines, Court Decisions
  • Feature article for Small/New Contractors
  • Practical Q&A Sections

Download & View Sample


DIGEST FEATURES
  • Experts' Discussion of "HOT" Contracting Issues
  • Analyzing a Cost Principle or Cost Accounting Standard
  • Pricing Strategies
  • Case Studies on Challenges to Government Findings

Download & View Sample


SUBSCRIBER BENEFITS
  • Free use of our "Ask the Experts" panel where subscribers can submit questions to or chat with our network of eminent consultants and attorneys.
  • Electronic access to all prior newsletters through 2000. We provide state-of-the-art word search Word and linked electronic index to all articles.
  • Mailed hard copies and electronic versions will provide timely access to all newsletters.

 Learn More

 Subscribe